Novapoint 19DCM in the ‘Software for Road Infrastructure’ magazine

20 December, 2012

Imagen

Novapoint is appearing in the supplement of World Highways & ITS International magazine. In a chapter titled ‘Novel Norwegian road development’ you can know more about the corridor project that is being developed with Novapoint 19DCM

Link to article:

page 6

http://www.ropl.com/digital/2012/software/flipviewerxpress.html

Groundbreaking IBIM approach in Norwegian joint road and rail project

20 November, 2012

Source: www.vianovasystems.com

With a holistic approach and very clear requirements for interdisciplinary 3D design modeling and collaboration, the Norwegian road and rail authorities literally pave the way for IBIM, “Infrastructure Building Information Modeling” in their ongoing E6-Dovrebanen Joint Project.

The result– given by extensive use of a joint 3D collaboration model and tight cooperation between the engineering consulting players Cowi, Norconsult and Aas-Jacobsen/ ViaNova – is better collaboration, great savings and better quality.

Some 100 km north of Oslo, along a stretch at lake Mjøsa, Norway´s largest lake, the E6 motorway and the Dovrebanen railway lie very close to each other.

Hence the Norwegian Public Roads Administration (NPRA) and the Norwegian National Rail Administration (NNRA) joined forces to plan and build the new E6 and Dovrebanen on this stretch holistically and concurrently.

Exemplary pioneering project

The engineering job is divided into three parcels, each contracted to COWI, Norconsult and Aas-Jacobsen/ Vianova respectively, with ViaNova Plan and Traffic as the contractual partner.

Based on the road authority NPRA´s new design guide, the so-called Handbook 138, the three consulting companies each individually design and model their infrastructure stretch multidisciplinary, and then coordinate their designs by means of a joint integrated collaboration model integrated into the design process – achieving common goals of collaboration, quality assurance and savings.

One project included in several

The Joint Project´s respective road and rail sections are both parts of larger projects in the region: The road stretch is part of the NPRA project E6 Gardermoen-Biri, while the rail stretch is a part of the project Dovrebanen, Eidsvoll-Hamar.

The actual construction of the project is also divided into three sections. Separate contractors are contracted for each section. Parcel 1 is assigned to Alpine Bau GmbH, Parcel 2 is assigned to Veidekke Hochtief and Parcel 3 is assigned to Hæhre Entreprenør.

The construction started in June 2012 – a total of approx. 22 km four-lane E6, 17 km double track railway, over 20 km local roads and 19 km bike and walking paths. The project also includes four-lane road tunnels totaling 3.6 km, railway tunnels totaling 4.6 km, two-level intersections with acceleration lanes, culverts and pedestrian bridges.

Savings and quality improvement

According to the builders, the way of organizing and carrying through the Joint Project will result in savings of several hundred million NOKs. One reason for this is shorter distances for moving soil and rock mass. Another reason is the way the design engineering is carried through and what this means in terms of efficiency and quality improvements.

Paves way for Infrastructure Building Information Modeling – IBIM

“This way of design engineering paves the way for BIM also in infrastructure projects”, says Ole Jacob Schia. He is responsible for 3D design and coordination at Norconsult and is one who knows the challenges of the project best.

“Based on the new Handbook 138 the project owners NPRA and NNRA set strict requirements for the use of 3D models”, tells Schia. “Both in terms of basic model data, files, discipline models, the coordination model, machine and survey data, update process in the construction phase, as well as “as-built” information”, he says.

Work methodology important

Since Handbook 138 was not 100 % finished at project start, it was however, while waiting for this, decided to agree upon common project documents to handle the structure, the process and the method of the 3D design modeling. The specifications were to help giving all three parcels the same structure of the discipline models, as well as the collaboration model.

Regarding the digital deliverables, there were no specific requirements for what software to use for the different 3D discipline models, just that the format of the deliverables should be DWG. As basis for the collaboration model was decided to use Novapoint Virtual Map, a common tool for design modeling and visualization. Novapoint Virtual Map converts multidisciplinary design data into a visually rich virtual reality model that everybody can understand and view interactively.

Virtual Map hence adds new dimensions into the design process.

Model-based design and engineering

With this as the basis, Cowi, Norconsult and Aas-Jacobsen/ViaNova each designed their respective 3D models for each discipline of the project – models that then all together form the whole project model and also provides the data necessary for the contractors to build the project.

The assembly means a dynamically updated virtual collaboration model of all design data from all disciplines. During the whole design process the model is updated constantly to reflect the current design status.

The NPRA and NNRA also had strict requirements for the 3D discipline models in terms of also being the basis for construction machine data and survey data for the contractors. 2D drawings will apply as supplementary information.

“This is a significant step towards full model-based engineering in which 3D design modeling is becoming increasingly important”, points out Norconsult´s Ole Jacob Schia.

By assembling all the discipline models into a full project model based on the Novapoint Virtual Map visualization system, holistic 3D interdisciplinary coordination and control could be created.

Interdisciplinary coordination and quality assurance

With a free viewer tool in Novapoint Virtual Map one can evaluate and control the whole 3D model of the project, and move freely around in the model, both above and below ground.

Viewing the design as a 3D virtual model gives the design process a whole new perspective.

“This way it is easy to view the total solution and do interdisciplinary coordination and assessment”, continues Schia. “Including automatic design collision control. It is much faster to detect design errors and eliminate them this way, than in the 2D world. The number of conflicts for construction is drastically reduced, whilst at the same time good aesthetic solutions is taken care of”.

Major benefits for the contractors

The collaboration model also provides a far better basis for the contractors, is the Joint Project´s experience. Planning and scheduling the work process can be done in a much better way, than just using 2D drawing-based documents.

The collaboration model contributes to improved quality assurance and cost control, and is additionally an excellent medium for the contractors, it is claimed.

“The contractors may use the collaboration model to understand and familiarize themselves with the project. This is obviously done much faster viewing the model, than using the approximately 700 drawings, which are also part of the construction basis for Parcel 2″, says Ole Jacob Schia.

Stein Slaatsveen, Project Manager at ViaNova Plan and Traffic, also highlights advantages for contractors using the 3D model:

“The collaboration model provides a much better understanding of the work to be done. For example their prizing calculations can be made more precise. In addition the contractors may retrieve the setting out data directly from the discipline models, providing flexibility in retrieving the data they really need”, he says.

Good organizing important

Slaatsveen believes also that the way of organizing the work is critical: “It is important to assign a head project coordinator who is responsible for driving the whole process and also assign one responsible for each discipline model”.

“All disciplines should be included early in the process”, he adds, and points out that the quality assurance of the solutions “the interdisciplinary coordination achieved through the collaboration model – significantly reduces the risk of errors. Structural design collision and conflict control becomes much easier and precise”.

Lifecycle model for the builders

Also for the public builders NPRA and NNRA, the collaboration model provides new opportunities – in the design engineering phase, follow-up during construction, as well as in the operational phase:

“We are very much in favor of this new way of working”, says engineering manager Henning Johnsen at the railway authorities NNRA. “The collaboration model makes it possible to detect and fix things much faster and earlier in the design process. Mistakes and interdisciplinary conflicts may as a result be very costly if they are first discovered at the construction site”.

“The joint 3D model is both an excellent communication tool and a conflict resolution tool”, emphasizes Johnsen. “Within the project as well as in relations with the public”.

As a communication medium the collaboration model is used actively internally in the project for inter-communication and planning activities, as well as externally with the builders, other stakeholders and the media.

“The visualization is equally suited to present the various model stages for landowners, politicians and authorities, as well as to discuss project details with discipline colleges”, he says.

“It will be really interesting to see what the future brings in terms of actual savings in the construction phase”, continues Henning Johnsen. “Especially in relations to how the construction managers will encounter change orders as a result of design conflicts between disciplines. It will be exciting to see what effects this will have”.

“Model-based engineering allows also for other disciplines to enter the process earlier”, he adds. “Decisive input may pop up earlier and lead to even better planning”.

“What´s more; model-based “as-built” information will also be very beneficial for auditing and maintenance purposes later in the infrastructure life cycle”, points out Henning Johnsen at NNRA.

Educational and useful

“The process of using the collaboration model has been educational as well as advantageous in the engineering design process”, states Gjermund Dahl, COWI´s 3D-responsible engineer in the Joint Project, and adds another benefit:

“It´s a challenging fact that it is the young engineers who are the most knowledgeable about 3D design and modeling in 3D, while it is the older ones who have the most experience, and to a higher extent, are capable of “seeing” interdisciplinary. The collaboration model also proves to be a good setting for coordination and sharing of knowledge between engineering designers”, he says.

Gjermund Dahl however calls for some more dynamics in the actual 3D model used:

“To create a good collaboration model is demanding and requires good, strict routines for the various disciplines to prepare and publish their model files. A more dynamic collaboration model would be helpful to provide even faster and more efficient design engineering”.

Having said that, this is something that is being worked very hard and persistently on by design tool developers. For example Vianova Systems. Vianova´s new generation IBIM technology, which is due for release later this fall, will provide new state-of-the-art, model- and process-based technology, allowing for full dynamics in the IBIM processes.

The BIM concept is finally becoming a proven practice also in the infrastructure segment, believes therefore the Norwegian road and rail authorities and the consultants Cowi, Norconsult and Aas-Jacobsen/ViaNova.

Their very positive experience in the E6-Dovrebanen Joint Project definitively shows that this is the way to go.

New norwegian blog to keep you updated about Novapoint

19 November, 2012

A new blog is available for users of Novapoint. It´s meant to give you tips, in addition to collecting relevant information so that your daily work is simplified. 

Imagen

 

Don´t forget to keep an eye on it, it´s very useful and interesting.

www.vianovasystems.no/Blogg

4 new functions in Novapoint Road 18.20 or 18.30

25 July, 2012

The new Novapoint 18.30 works on AutoCAD 2013 platforms. This release has the same functionality as Novapoint 18.20 FP2a that was released recently.

Let´s have a look into the new road functionality that has this important release.

1. Dynamic link between two road models

You can now automatically create an alignment on the edge of a road surface or for all the end surfaces on the right/left side of a road. These alignments are automatically updated if you change and rebuild the road model. Right click on a surface in the Cross-section Viewer:

Four new choices in the dialog:

  • Save/update end of surface as alignment: creates an alignment along this surface edge for the whole project. The alignment is stored to the DTM to Group 99991 and the alignment is named after the Road model and surface name P-2.1_100 – Surface edge 2.1 and project 100

  • Erase alignment created from end surface: deletes the alignment from the DTM.
  • Save road edges as alignment: creates an alignment based on the end surface on the right and left side of the road model.

The alignment is stored to the DTM to Group 99991 and the alignment is named after the Road model and surface name P_-9.9_100 – End Surface edge left side and project 100 and P_9.9_100 – End Surface edge right side and road model 100. This surface can vary depending on whether the road is on cut or fill.

  • Erase Road edge alignment: deletes the alignment from the DTM.

These alignments can be for example linked to an external road model:

Before & After:

If the active road model is now adjusted the dynamic link is automatically updated.

Note: As these alignments are dynamically linked to the road model they cannot be used in the same road model.

The dynamic link can be turned off/on in Model – Settings – Elements Tab by selecting/deselecting the Update connection alignments.

2. Multiple road model interface – External models

External models can now be edited and calculated via the Cross-section Viewer in your active road model. Surface description on an external model can be edited by right clicking on the road surface. Road Pavement and Advanced Pavement for the external model can also be edited by clicking on a road pavement for the external model.

External models must be added/removed by selecting File – Properties and the External models tab:

When selected they will be shown in the Cross-section Viewer and can be edited in the same way as the active model. Right click on a road surface in an external model:

Select the surface for the external road model (in white) and the Road Surface description for the external road model opens. This can now be edited. The same applies to the road pavement for the external road model.

When the Calculate external models is activated in the Model – Settings and Elements tab:

All models will be calculated starting with the active model and then the first external model in the list and ending with the active road model again. After the first model is calculated select Close and the next model will build. Continue until all road models have built. The automatic calculation of the external models can be turned off by deselecting the Calculate external models.

3. Advanced pavement description

The new dialog can be accessed from the road model menu, Data – Advanced Road Pavement… or by clicking on a road pavement layer in the Cross section viewer and selecting Advanced pavement


When selected from the Cross section viewer the dialog will open at the pavement layer selected:

It is now possible to define a pavement layer in the same way as the Road bed. The number of surfaces available has been increased to 15 (16 for the Road bed).

Note: there is no End Surface for the other pavement layers. All pavement layers with the exception of the Road bed should end against the Inner slope/ditch or cut/fill line or sent up to the layer over. A pavement layer will always stop at the layer over and then follow that layer. Pavement layers cannot be defined outside the body of the road.

Note: A road pavement layer should not be sent through a lower layer.

Right click on either the Left or Right side of a pavement layer and the following choices are available (the choices are self-explanatory):

Right click on a Surface and the same choices are available:

Note: As for the Advanced Road Bed description a user defined pavement layer must have a complete definition for both sides or the result may not be correct.

4. Build of Road and Rail models

The build of a road or rail model can be started from the model menu under Model – Build, from the Cross-section viewer or by selecting Apply in a number of dialogues. Under is a description of what each build does.

Model – Build from the model menu.

The Build dialogue is opened and Wire frame and Quantity calculation can also be calculated. When external models are attached and the setting Calculate external models is selected (Model – Settings – Element) the active model is built first then each of the external models in the same order as they have been attached and then the active model once more. The build dialogue is opend for each model and any calculation errors can be controlled.

When only the Update connection alignments is selected the active model is calculated twice, once to update any connected alignments and once more to update the viewer.

Build from the Cross-section viewer.

When the button  is selected the whole project is calculated and the result build dialogue for the active model is opened.

When external models are attached and the Calculate external models setting is selected the active model is calculated and the result dialogue is shown, when this is closed the external models are calculated followed by the active model once more in silent modus, no result dialogue is shown.

Note: Connection alignments for external models will not be updated.

When only the Update connection alignments is selected the active model is calculated and the result dialogue is shown, when this is closed the active model is calculated once more in silent modus, no result dialogue is shown.

When the button is selected only the selected cross section in the viewer is calculated and the result from earlier calculation including the quantities and wire frame are deleted.

External models are not calculated.

Note: Connection alignments will not be updated.

When is selected the whole project is calculated in silent modus. No error messages are shown and connection alignments in external models are not updated.

Note: If you are working with connection alignments it is strongly recommended that the Model – Build method is use.

Checking the visual impact of an Industrial Park

11 April, 2011

These models were created in the framework of a research carried out by EGICAD, department of the University of Cantabria Region in Spain for the years 2003 and 2004 with Novapoint Virtual Map. To build models Autodesk Land Desktop was used and to make the interactive 3D visualization the chosen software was Novapoint Virtual Map.

The purpose of the project was to create an industrial park in Gornazo (Miengo, Cantabria, Spain) near the service area of ​​the A-8 highway. For this study, we developed an interactive 3D model that includes the City of Miengo almost completely and was used to detect all possible views of the buildings of the park from anywhere, especially from different towns, from areas of high landscape value, as well as from the nearby highway.

The model was used to evaluate the effectiveness of the proposed solution to minimize its visual impact. The solution was a wooded area disposed between the road and the buildings of the estate.

In these studies a group of students were involved and were trained in the creation of models in AutoCAD and processing them using the Virtual Map Model Builder to create interactive models. This project involved the collaboration of Vianova Systems Spain SL which provided the software. As part of this research, the author participated in a seminar held in Vianova headquarters in Oslo, Norway.

Source: Reinaldo Togores, www.togores.net

Video no.1: Projected Industrial park

Video no.2: Area of the City of Miengo

Video no.3: Path made following the Highway, Industrial park is shown without vegetation barrier.

Video no.4: Same path as previous video but with a vegetation barrier between highway and park.


Follow

Get every new post delivered to your Inbox.